Synthetic extended title for an unusually complex cross-functional operating review, including multiple regions, jointly accountable teams, a revised delivery window and the full descriptive name without any ellipsis
- Owner
- Priya Raman
- Reported
- 8 Sep 2026
- Next review
- 15 Sep
- Window opens
- 1 Nov 2026
At risk
Changed from On trackThe penetration test is now the entire critical path. Our vendor cannot start before 6 October and the 10 October readiness assessment needs their report, so a two-week slip in the test is a two-week slip in the window. Everything else is on or ahead of schedule.
Since last week: evidence automation closed on 21 August and the access review passed 60%. The pen test moved from 22 September to 6 October when the vendor reassigned our team — that one change is why this is amber.
Needs a human
-
01
Approve the second pen-test vendor, or accept the slip
Decision by Synthetic jointly accountable owner with a very long full department name Needed by Synthetic jointly accountable owner with a very long full department name
The second vendor can start 22 September for £9,400 more. Doing nothing moves the window to 15 November, pushing the report past the two enterprise renewals that asked for it.
-
02
Sign off the standing-access model
Decision by Marcus Lee & Security Needed by 19 September
Break-glass only, or named exceptions with a quarterly review — both are built. The access review cannot close until one is chosen, and it is the last thing between us and 104 of 104 controls.
- Milestones
- 3 of 7
- Open blockers
- 3
- Days to window
- 54
- Budget used
- 68%
complete · 1 in progress
1 needs a decision this week
opens 1 November
£61K of £90K
Milestones
- 12 JUN
Scope & control mapping
Done - 24 JUL
Policy set approved
Done - 21 AUG
Evidence automation
Done - 19 SEP
Q3 access review
In progress · 60% - 6 OCT
Penetration test
At risk · slipped 14d - 10 OCT
Readiness assessment
Planned - 1 NOV
Observation window opens
Planned
Scope
Controls implemented87 / 104
84% · the remaining 17 are all access-related
Evidence collected automatically61 / 104
59% · target is 75 by the window opening
Policies approved22 / 22
100% · signed off 24 July, no changes since
Blockers
-
Pen-test vendor cannot start before 6 October
BlockingNeeds: approval to run the test with our second vendor at +£9,400, or a decision to move the observation window to 15 November.
-
Nine engineers still hold standing production access
BlockingNeeds: the standing-access model signed off. Break-glass tooling has been built and tested since 2 September — this is waiting on a decision, not on engineering.
-
Two subprocessors have no countersigned DPA
WatchingNeeds: countersignature from both vendors. Chased three times; escalate to their account teams if open on 22 September.